Photo: Hunter Trick, 2023, via Wikimedia Commons (CC BY-SA 4.0)
The short answer: TSMC, the world’s largest contract chipmaker and the factory behind chips from Apple and Nvidia, has filed plans for a possible $22.6 billion chip plant on about 3,232 acres in southern Brazos County, Texas, just outside College Station. The plant would make 2-nanometer-class chips, TSMC’s newest generation, for AI, data centers and phones. The filing promises 2,099 direct jobs averaging about $133,000 a year. It is not a done deal. TSMC says a Texas property tax break is the "determinative" factor, the land is not bought, and Arizona, where TSMC already makes chips, is still the alternative.
The application reached the Texas Comptroller on Monday, Nov. 23, 2026, and Brazos County confirmed it the same day. Posts on X about TSMC and Texas went from about 20 a day to more than 400 by Tuesday morning. Here is what the 128-page filing actually says, why College Station, what TSMC would get, and what has to happen before anything gets built.
What TSMC filed
The paperwork is a Jobs, Energy, Technology and Innovation (JETI) application, number J0055, filed by TSMC Arizona Corporation, the U.S. arm that runs TSMC’s Phoenix plants. It calls the project the "TSMC Texas Advanced Semiconductor Manufacturing Campus" and describes "one or more front-end semiconductor fabrication facilities," meaning fabs that turn blank silicon wafers into finished chips, plus the utility plants and water systems that feed them.
The campus would make "leading-edge logic semiconductors utilizing 2-nanometer and/or more advanced process technologies." Logic chips are the processors that do the computing, as opposed to memory. TSMC began volume production of its 2-nanometer process, called N2, in Taiwan in late 2025, and it supplied 8% of the company’s wafer revenue in the third quarter of 2026, CFO Wendell Huang said on the Oct. 15 earnings call. In the United States, TSMC’s Arizona site makes 4-nanometer chips today, and its third Phoenix fab, the first slated for 2-nanometer and the newer A16 process, is due for volume production by the end of the decade.
The numbers in the filing
The economic analysis attached to the application, prepared by the Austin consultancy Impact DataSource, lays out the plan year by year. Construction would start in 2027 and run through 2031. Most of the money goes into tools, not buildings: about $14.02 billion for machinery and equipment and $8.60 billion for buildings and other property, for a total of $22,619,235,774.
| Year | New TSMC hires | Planned investment | Stage |
|---|---|---|---|
| 2027 | 0 | $0.73 billion | Construction |
| 2028 | 757 | $2.59 billion | Construction |
| 2029 | 1,110 | $5.93 billion | Construction |
| 2030 | 232 | $9.05 billion | Construction |
| 2031 | 0 | $3.36 billion | Construction |
| 2032 | 0 | $0.96 billion | First tax-break year |
Hiring would start in 2028 and reach 2,099 jobs by 2030. The filing puts the average salary at $133,026 in its first year, not counting bonuses, and assumes 2% raises after that. That is far above the $73,603 the program requires for this project. The analysis also estimates that construction spending would support about 2,500 construction jobs in 2027, 8,900 in 2028 and 18,100 in 2029. Those numbers come from a standard formula applied to construction costs of about $5.6 billion, not from a hiring plan.
Where it would go, and why College Station
The site covers 3,231.8 acres in Brazos County Precinct 1, generally north of Koppe Bridge Road and west of I&GN Road, according to KBTX, the College Station TV station that reported the filing Monday. Most of it sits outside College Station city limits but inside the College Station school district and the city’s extraterritorial jurisdiction. Some parcels have homes and barns, and the filing says TSMC plans to demolish any it buys.

Photo: Oldag07, 2022, via Wikimedia Commons (CC BY-SA 4.0)
The workforce. Officials told KBTX that TSMC picked the area for its closeness to Bryan-College Station, Texas A&M University’s engineering workforce, quality of life and an international airport. A fab needs a steady supply of process, equipment and chemical engineers, and technicians to keep its tools running around the clock.
The neighbors. Brazos County borders Grimes County, where SpaceX plans its own chip complex, called Terafab, with Tesla and Intel as partners. SpaceX’s filings put Terafab’s first phase at about $55 billion and a full four-phase build at as much as $119 billion. In October, Musk confirmed talks with TSMC about the project and wrote on X, "Maybe TSMC subleases part of the Terafab if they want, but nothing more than that."
Power and water. Bryan Texas Utilities serves the area today and Wellborn Special Utility District provides water. KBTX reported that TSMC intends to buy its water from a third party and that county officials expect no impact on local water resources. Fabs use large volumes of ultra-pure water, and TSMC says its Arizona site is building a reclamation plant, due in 2028, to recycle 90% or more of what it uses. For more on how big tech campuses handle heat and water, see our guide to how data centers stay cool.
As an Amazon Associate, Aglena earns from qualifying purchases.
The tax break it hinges on
JETI was created by House Bill 5, passed by the Texas Legislature in 2023. For 10 years, it cuts the taxable value a school district can use to collect maintenance and operations tax, the part of the school tax that pays for teachers and daily costs. For this project the cut is 50%. Under the school-finance formula, state aid largely replaces the money the district does not collect, though critics note the backfill is not a guaranteed dollar-for-dollar match.
The Comptroller’s summary, posted Nov. 24, puts the stakes in dollars. Over 20 years, College Station ISD’s maintenance and operations levy on the project would be about $759.3 million without the limit and $405.2 million with it, a gross tax benefit to TSMC of about $354.1 million. The incentive years would run from 2032 through 2041, and TSMC would have to post a $35.4 million performance bond. The project would still pay the school district’s debt-service tax, county tax and emergency-services tax on the full value, unless the county grants its own abatement.
TSMC’s filing is blunt about why the break matters:
Absent the requested limitation, the Texas site would remain at a severe competitive disadvantage compared to the Arizona alternatives, which already offer established operational efficiencies and lower capital risk.
TSMC Arizona Corporation, JETI application to the Texas Comptroller
The filing says TSMC is "considering the potential acquisition and development of a new land parcel in Arizona" instead, citing its North Phoenix workforce, suppliers and government relationships there. In the recommendation packet, the Comptroller’s office determined that the limit "is a compelling factor in a competitive site selection" and that without it TSMC would not make the investment in Texas.
Is it really happening?
Not yet, and the filing says so several times. These are the open questions.
The land is not bought
County officials said the parcels are under contract, but KBTX found county records show no purchase. The filing says TSMC has only "authorized agents to enter into nonbinding agreements" that "in no way commit the company to acquire land or make a final site selection decision." Asked by the Comptroller to list its agreements, TSMC said the only signed one was with a real estate broker.
Texas is competing with itself, too
Local officials told KBTX that Brazos County is also competing with Sherman in North Texas, home to Texas Instruments’ 300-millimeter wafer plants, and with Arizona. TSMC has not made a final investment decision.
What TSMC has said in public
On TSMC’s Oct. 15 earnings call, Chairman and CEO C.C. Wei said the company was looking "outside Arizona" for more U.S. capacity: "That Texas is one. So we send the teams to Texas to do all the evaluation." He added that TSMC was also talking with a customer building Terafab and that "if we have any solid conclusion, we will share with you."
What happens next
The Comptroller has now reviewed the application and posted its recommendation packet. Under the JETI process, the agreement still needs approval from the governor’s office and the College Station ISD board of trustees, which must hold a public hearing and vote. KBTX reported the school district’s part could begin as early as mid-December. Any Brazos County tax abatement would be a separate decision by the Brazos County Commissioners Court, with its own public meetings.
Brazos County said it would hold a town hall to answer residents’ questions and launch a web page with meeting dates, but it had not set a date as of Nov. 24. County Manager Trevor Lansdown called the project a "potential transformational opportunity" and said, "Our goal is to turn this potential project into lasting prosperity and an even brighter future for Brazos County."
How it fits TSMC’s U.S. plans
TSMC picked Phoenix for its first advanced U.S. plant in 2020, and its planned Arizona investment has grown from $12 billion to $265 billion, according to the company. The plan there covers six chip fabs, two advanced packaging plants and a research center, and more than 3,500 people work at the site today. The first fab began high-volume production on 4-nanometer chips in late 2024. Wei said on the October call that the second fab has finished construction and will start volume production in the third quarter of 2027, slightly ahead of schedule.
Wei also said TSMC has nearly 20 fabs in progress worldwide, including "another five to six fabs overseas." The driver is AI. TSMC manufactures the processors inside Nvidia’s data center GPUs (see our explainer on how GPUs became the engine of AI), and buyers are signing enormous deals to lock up that hardware, such as SpaceX’s $44 billion Nvidia chip deal. A Texas campus would be TSMC’s second advanced manufacturing hub in the United States.
The bottom line
TSMC has put a real number on a Texas chip plant: $22.6 billion, 2,099 jobs and 2-nanometer chips near Texas A&M, with construction from 2027 and a first tax-break year in 2032. But by its own account the plan depends on a 10-year school tax cut worth about $354 million, land it hasn’t bought, and a final decision it hasn’t made, with Arizona as the alternative. The next public markers are the College Station ISD hearing and vote and Brazos County’s town hall.
Further reading

Chip War by Chris Miller
The history of how chipmaking ended up concentrated in a few companies, with TSMC at the center.

The Nvidia Way by Tae Kim
How Nvidia became TSMC’s biggest AI customer and why its chips drive demand for new fabs.

NVIDIA Jetson Orin Nano Super Developer Kit
A small AI computer for running models at home, built around an Nvidia chip.

Samsung 990 PRO 2TB NVMe SSD
A fast PCIe 4.0 drive for a PC upgrade, with storage chips at the other end of the semiconductor business.